YearElectric wind turbines installedPower MWManufacturerNumber of wind turbinesManufacturer
2002Virtsu I windpark1,8Enefit Green AS3Enercon
2005Pakri wind farm18,4Enefit Green AS8Nordex
Esivere 8Enefit Green AS4Enercon
Läätsa 3Telewind AS6Siemens
2007Nasva wind farm1,6Baltic Wind Energy OÜ2Vestas
Viru-Nigula 21Enefit Green AS7Winwind
Ruhnu (Sjustana) 0,15Enefit Green AS2Vestas
Türju0,3Rotorline OÜ3
2008Virtsu wind farm0,8Enefit Green AS1Enercon
Virtsu II 6,9Enefit Green AS3Enercon
Esivere I 12Skinest Energia AS4Winwind
2009Aulepa windpark – I stage39Enefit Green AS13Winwind
Vanaküla tuulepark9Enefit Green AS3Winwind
Tooma I tuulepark16Enefit Green AS8Enercon
2010Virtsu III wind farm6,9Enefit Green AS3Enercon
2011Nasva windgenerator I2,3Baltic Workboats AS1Siemens
Aulepa II 9Enefit Green AS3Winwind
Aseriaru24Enefit Green AS8Winwind
2012Narva wind farm39Enefit Green AS18Enercon
Paldiski 45Enefit Green AS18GE Energy
Sikassaare1,5Stacey OÜ3Enercon
2013Ojaküla wind farm6,9Enefit Green AS3Enercon
Nasva II3,6Baltic Workboats AS1Siemens
2014Tamba wind farm6Tuuleenergia OÜ3Enercon
Mäli 12Tuuleenergia OÜ4Enercon
Aburi 1,8OÜ Green Electric1Vestas
Salme II 3Eleon AS1Eleon
2015Torgu windgenerator0,66Meritreid OÜ1Vestas
2016Tooma II wind farm7,05Enefit Green AS3Enercon
2020Varja I stage, Purtse wind farm10Eesti Ühistuenergia OÜ5Vestas
2023 Purtse Windpark21Enefit Green AS5Vestas
Saarde Windpark39Utilitas Wind OÜ9Vestas
Aseri 4,7Utilitas Wind OÜ2 Enercon
2024Aidu Windpark 75Aidu Wind Park OÜ17Vestas
Total 457176